Since concrete is the most used building material, cement which acts as a binder is one of the most important building elements which has cost implications if not well optimized. You may want to do a check of the cement quantity for your building project. Kindly follow the process below in this case:

Assumptions:

Slab area= 180 square meters

Slab thickness= 150mm (6 inches)

Lenght of beam = 130 meters

Floor slab cement calculation

Number of bags of cement required= Volume of concrete x number of bags per cubic meters

Number of bags per cubic meter varies between 4 and 7 depending on the target mix strength

1:2:4 mix= approx 7 bags of cement per cubic meter

1:3:6 mix= approx 4 bags of cement per cubic meter

5 bags of cement per cubic meter is optimal considering cost and quality

Volume of slab= Slab Area x Slab thickness

Slab area= 180 sq.m

Thickness used= 150mm

Volume of slab= 180 x .15m

27m3

Beams and slabs are mostly casted together, hence:

Volume of beams= Total length of beams x width of beam x Height of beam

=130m x 0.225m x 0.3m= 8.8 m3

Total volume= 35.8 cubic meters

Cement bags required= 35.8 cubic meters x 5 bags per cubic meter

= 179 bags of cement

About the author

nighouseplans

Sharing practical ideas on architecture, building construction, home planning and better living.

View all articles
Continue reading

You Might Also Like

View all articles →
Join the conversation

6 Comments

Eugine Aug 7, 2023 at 4:37 pm
Reply

This is so difficult

nighouseplans Aug 7, 2023 at 8:26 pm
Reply

Dear Eugine, it’s not difficult once you can derive the volume and multiply by the required factor.

Ukpeowe John Nov 18, 2023 at 4:24 am
Reply

Nice one here.

How do you now determine the sand components for same quantity of cement.

nighouseplans Dec 11, 2023 at 4:42 pm
Reply

Dear Ukpe, Multiply the volume to be casted by a factor of 1.7.
This gives 35.8×1.7= 60.86 tonnes of sand.

Favour Jan 17, 2024 at 2:30 pm
Reply

35.8 x 1.7= 60.86
So the above is wrong.

nighouseplans Jan 24, 2024 at 7:16 pm
Reply

Thanks for the observation favour, It’s been updated.

Leave a Comment

Your email address will not be published.

Scroll to Top